Grosse Ile High School - 2016 Bond Update

Below you will find information regarding our bond progress. 

PDF Document2017 Scope of Work - First Story
PDF Document2017 Scope of Work - Second Story

Completed Work

 

  • 324 Chromebooks purchased and deployed without touch screens
  • 96  touch screen Chromebooks purchased and deployed for the math and science departments
  • 95 Desktop computers in Music Lab, Library, and Lab 117
  • Cisco network switches upgraded
  • UPS upgrade/replacement (Uninterruptible  Power Supply - all network equipment power)
  • 29 Staff Chromebooks and PCs
  • Electrical surge suppressors

Work Scheduled for Summer of 2017

 

  • Painting of Labs, Classrooms
  • Carpet in Labs
  • All new lockers  with locks attached
  • Ceilings replaced in collabrative work spaces
  • Roofing replacement/repairs
  • Exterior lighting replaced/repaired
  • Sidewalk repairs
  • HVAC updates/repairs/replacements
  • Remounting/replacing/purchasing of whiteboards for classrooms
  • New data projectors
  • New document cameras
  • More Chromebooks
  • Monitors in lobby and hallways
  • New doors and windows
  • Printing update
  • ​HD securit cameras added to interior and exterior
     
  • 1 new science lab
    • Monitor
    • Casework
    • Chemical rated counter tops, table stations, and teacher station
    • Paint
    • Flooring
    • Ceiling
    • Lighting
  • Collaborative Work Spaces
    • New carpet
    • New paint
    • New furninature
    • Monitors
    • Projectors
    • Whiteboards

Work Scheduled for Summer of 2018

 

  • Athletic field upgrades including Track, Baseball, and Softball locations
  • Student parking lot
  • Student parking lot LED lighting upgrade